Below are 30 real practice questions for the Scrum Scrum Master I (PSM-I) exam. Each question shows the correct answer and a detailed explanation when you reveal it. Use these to benchmark your readiness — if you score below 70% on these 30 questions, plan for at least 4 more weeks of study before booking.
PSM-I Practice Questions
- FreePracticeQuiz.questionLabelScrum FrameworkYou have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (choose two)AThere should be six Product Owners, one for each Scrum Team.BThere should be six Product Owners, reporting to a chief Product Owner.CThe product has one Product Backlog.DEach Scrum Team should have a separate Product Backlog.EThere should be only one Product Owner.
- FreePracticeQuiz.questionLabelScrum RolesA Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (choose two)AEnsuring that the most valuable functionality is produced first, at all times.BInteracting with stakeholders.CProviding the Scrum Team with detailed specifications.DDescribing features as Use Cases.ECreating detailed functional test cases.
- FreePracticeQuiz.questionLabelDefinition of DoneUser documentation is part of your Definition of Done. However, there aren't enough technical writers for all teams. Your Developers don't have a technical writer. What should you do?AForm a separate team of technical writers that will work on an on-demand basis for the various Product Owners. Work order will be first in, first out.BLet the user documentation remain undone and accumulate until after the last development Sprint. It will then be done by any available technical writers.CWait until you have a technical writer on your Scrum Team to take care of this.DYour Scrum Team is still responsible for creating user documentation. In this case, the Scrum Team members will write it.
- FreePracticeQuiz.questionLabelScrum MasterYou are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a technical specialist who is external to the teams. What are two key concerns for the Scrum Master to take into account in this situation? (choose two)AThe desire to maintain a stable velocity.BThe benefit of Developers figuring out a solution for themselves.CThe need to have enough work to keep all Developers busy.DThe ability of the Developers to produce integrated Increments.
- FreePracticeQuiz.questionLabelScrum EventsThe Product Backlog is ordered by:AThe Product Owner with the most valuable items placed at the top.BRisk, where safer items are at the top, and riskier items are at the bottom.CItems are randomly arranged.DSize, where small items are at the top and large items are at the bottom.
- FreePracticeQuiz.questionLabelSprintWhat happens if the Scrum Team cannot complete its work by the end of the Sprint?AThe Sprint is extended and future Sprints use this new duration.BThe Sprint length holds and the Scrum Team continuously learns what is actually possible to do within a Sprint of this length.CThe Sprint is extended temporarily. Lessons are taken to ensure it doesn't happen again.
- FreePracticeQuiz.questionLabelScrum EventsWhich topics should be discussed in the Sprint Review?AThe Scrum process, and how it was used during the Sprint.BCoding and engineering practices.CSprint results.DAll of the above.
- FreePracticeQuiz.questionLabelScrum TeamA member of the Scrum Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?AAdd security to the Definition of Done.BTell the Product Owner to stop further development of features until the issues are fixed.CCreate a Product Backlog item for security.DGo check with the testers.EAsk the person to share the issue with the team as soon as possible.
- FreePracticeQuiz.questionLabelScrum TeamWhat does it mean for a Scrum Team to be cross-functional?AThe Scrum Team includes not only Developers but also business analysts, architects, and testers.BThe Scrum Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an Increment of software.CDevelopers on the Scrum Team work closely with business analysts, architects, Developers and testers who are not on the team.DThe Scrum Team is a virtual team drawing from separate teams of business analysts, architects, Developers and testers.
- FreePracticeQuiz.questionLabelScrum ArtifactsSprint burndown charts are an efficient tracking tool, because they show:AAn estimate of the total work remaining for the Sprint.BHow much effort has gone into a Sprint.CHow many hours have been worked by each Scrum Team member.DHow many Product Backlog items remain.
- FreePracticeQuiz.questionLabelScrum ArtifactsHow much work must a Scrum Team do to a Product Backlog item it selects for a Sprint?AA proportional amount of time on analysis, design, programming, testing, and documentation.BAs much as it can fit into the Sprint. Any remaining work will be transferred to a subsequent Sprint.CAll development work and at least some testing.DAs much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the Definition of Done.
- FreePracticeQuiz.questionLabelScrum EventsWhich statement best describes the Sprint Backlog as outcome of the Sprint Planning?AIt is a complete list of all work to be done in a Sprint.BEvery item has a designated owner.CEach task is estimated in hours.DIt is the Scrum Team's plan for the Sprint.EIt is ordered by the Product Owner.
- FreePracticeQuiz.questionLabelScrum ArtifactsIf burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate? (choose the best answer)AThe evolution of the cost spent on the project.BWhen all work will be completed to the Scrum Team can be released for other work.CWhen the work remaining will likely be completed if nothing changes on the Product Backlog or the Developers.DWhen the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.
- FreePracticeQuiz.questionLabelScrum TeamWho is responsible for engaging the stakeholders? (choose the best answer)AThe Business Analyst.BThe Developers.CThe Team Manager.DThe Project Manager.EThe Product Owner.
- FreePracticeQuiz.questionLabelScrum EventsAt the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the Definition of Done. What two things should happen with the undone Product Backlog item? (choose the best two answers)AIf the stakeholders agree, the Product Owner can accept it and release it to the users.BPut it on the Product Backlog for the Product Owner to decide what to do with it.CReview the item, add the Done part of the estimate to the velocity and create a Story for the remaining work.DDo not include the item in the Increment this Sprint.
- FreePracticeQuiz.questionLabelScrum TeamWhich two of the following are true about the Scrum Master role? (choose the best two answers)AAt the Sprint Review, the Scrum Master identifies what has been "done" and what has not been "done".BThe Scrum Master teaches the Developers to keep the Scrum meetings to their time-box.CThe Scrum Master helps those outside the team interact with the Scrum Team.DThe Scrum Master assigns tasks to Developers when they need work.EThe Scrum Master is responsible for updating the Sprint Burndown.
- FreePracticeQuiz.questionLabelScrum TeamWhat are three benefits of self-management? (choose the best three answers)AIncreased creativity.BIncreased rule compliance.CIncreased accuracy of estimates.DIncreased self-accountabilityEIncreased commitment.
- FreePracticeQuiz.questionLabelScrum EventsWhich three of the following are time-boxed events in Scrum? (choose the best three answers)ARelease Testing.BRelease Retrospective.CSprint Retrospective.DSprint Planning.ESprint Testing.FSprint 0.GDaily Scrum.
- FreePracticeQuiz.questionLabelScrum TeamWho is responsible for clearly expressing Product Backlog items? (choose the best answer)AThe Scrum Master, or the Scrum Master may have the Developers do it.BThe Scrum Master.CThe Product Owner.DThe business analyst who represents the Product Owner in the Scrum Team.
- FreePracticeQuiz.questionLabelScrum TeamWhat is the best suited structure for Scrum Teams in order to produce integrated Increments? (choose the best answer)AEach Scrum Team works only one technical layer of the system (e.g. GUI, database, middle tier, interfaces).BEach Scrum Team develops functionality from beginning to end throughout all technical layers.
- FreePracticeQuiz.questionLabelScrum EventsWhy should the Product Owner be present at the Daily Scrum? (choose the best answer)AHe/She doesn't need to be there.BTo hear about impediments in functionality.CTo represent the stakeholder's point of view.DTo participate as a Scrum Team member.
- FreePracticeQuiz.questionLabelScrum TeamWhat two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (choose the best two answers)AInvolve the complete Scrum Team.BUse coaching techniques; such as open questions and active listening.CAsk an external technical specialist to make the decision.DSend every team member to the company's Human Resources department to express their concerns.
- FreePracticeQuiz.questionLabelScrum ArtifactsWhat enhances the transparency of an Increment? (choose the best answer)ADoing all work needed to meet the Definition of DoneBReporting Sprint progress to the stakeholders dailyCKeeping track of and estimating all undone work to be completed in a separate Sprint.DUpdating Sprint tasks properly in the electronic tracking tool.
- FreePracticeQuiz.questionLabelScrum TeamWho determines how work is performed during the Sprint? (choose the best answer)AArchitects.BThe Scrum Team.CThe Scrum Master.DSubject matter experts.EThe Developers managers.
- FreePracticeQuiz.questionLabelScrum EventsWhen does the second Sprint start? (choose the best answer)AOnce the architectural changes for the second Sprint have been approved by the senior architect.BAfter the Product Backlog for the second Sprint has been selected.CImmediately after the first Sprint.DAfter the customer completes acceptance testing of the first Sprint.
- FreePracticeQuiz.questionLabelScrum ArtifactsWhat is included in the Sprint Backlog? (choose the best answer)AUser Stories.BTasks.CUse Cases.DTests.EAny of the above (or others) which are a decomposition of the selected Product Backlog items.
- FreePracticeQuiz.questionLabelScrum TeamWhich of the following are true about the Product Owner role? (choose the best two answers)AThe Product Owner is one person.BThe Product Owner is accountable for ordering the Product Backlog.CMultiple people can share the Product Owner role on a Scrum Team.DThe Product Owner role can be played by a committee or a team of people.
- FreePracticeQuiz.questionLabelScrum ArtifactsTrue or False: When multiple teams work together on the same product, each team should maintain a separate Product Backlog.ATrue.BFalse.
- FreePracticeQuiz.questionLabelScrum TeamIf two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team? (choose the best answer)AIts productivity is likely to decrease.BIts productivity is likely to stay the same.CIts productivity is likely to increase.
- FreePracticeQuiz.questionLabelScrum EventsA Scrum Master is introducing Scrum to a new Scrum Team. The Scrum Team has decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take? (choose the best answer)ACall a meeting between the Scrum Team and senior management.BComply with the decision of the self-managing team.CConsult with the Product Owner to see how he/she feels about the situation.DBegin facilitating productive and useful Sprint Retrospectives.
Ready for the full PSM-I exam?
Get all 250+ Questions, timed simulation, and weak-area analytics. Plans from $2.99 — credits never expire.
Frequently Asked Questions
Are these real PSM-I practice questions?+
Is the PSM-I exam hard?+
How many questions are on the real PSM-I exam?+
Do I need to sign up to use these questions?+